1. |
Applications for consent
under Water, Air & Hazardous Waste will be available on
Rs.50/- in Sub-Regional Offices |
Office Working Days 11:00 A.M. to 1:00 P.M. & 2:00 P.M. to 4:00 P.M. |
Sub-Regional Officers
Office |
|
2. |
Acceptance of application & Receipt |
Same Day |
Sub-Regional Officers
Office |
3. |
Time to Communicate the
discrepancies to applicant |
Three days |
Sub-Regional Officers
Office |
4. |
Time for Verification of site &
other Technical details after Completion of discrepancies |
Fifteen days |
Field Officer Of Concern Sub-Regional Office |
5. |
Time for Grant of Consent after verification
(Based on Capital Investment) |
|
a |
Simplified Consent(Pollution
free SSI) |
Three days (After completion
of Descripancies & Verification Report) |
Sub-Regional Officer |
|
| b |
Green Consent- Investment |
| |
Rs.3 Crores |
Six days |
Sub-Regional Officer |
|
| Rs.3 Crores to 10 Crores |
* One & Half
Month |
Regional Officer |
|
| Rs.10 Crores to 500 Crores |
* Two
Months |
Member Secretary, M.P.C.Board,
Mumbai |
|
| Above Rs.500 Crores |
|
* Consent
Appraisal Committee M.P.C. Board, Mumbai |
|
| c |
Orange Consent-Investment |
| |
Upto Rs.5 Crores |
* One
& Half Month |
Regional Officer |
* One
Month After receipt of minutes of Consent Appraisal Committee |
| Rs.5 Crores to 100 Crores |
* Two
Months |
Member Secretary, M.P.C.Board,
Mumbai |
|
| Above Rs.100 Crores |
* One Month After
receipt of minutes of Consent Appraisal Committee |
* Consent
Appraisal Committee M.P.C.Board, Mumbai |
|
| d |
Red Consent-Investment |
| |
Upto Rs.15 Crores |
* Two
Months
|
Member Secretary, M.P.C.Board,
Mumbai |
|
| Above Rs.15 Crores |
|
* Consent
Appraisal Committee M.P.C.Board, Mumbai |
|